1. Purpose

Ensure consistent strength, finish and quality of MIB 6-inch bricks.

2. Who Is Responsible

3. When To Use This SOP

At the start of every MIB 6-inch batch, before feeding the machine.

4. Visual Process Flow

flowchart TD
A[Confirm product: MIB 6-inch] --> B[Check materials]
B --> C[Measure recipe]
C --> D[Dry mix]
D --> E[Add water gradually]
E --> F[Check mix consistency]
F --> G[Start first 20 bricks]

5. Step-by-Step Visual SOP

  1. Confirm product is MIB 6-inch before mixing.
  2. Check red soil, m-sand dust, cement and water.
  3. Use the approved 6-inch mix ratio only.
  4. Add water gradually โ€” do not make the mix too wet.
  5. Mix evenly before feeding the machine.
  6. Produce the first 20 bricks.
  7. Continue only after First 20 Bricks Approval (FIRST20_QC_V1).

Recipe (approved values โ€” fill in)

Red soil:    ___
M-sand dust: ___
Cement:      ___
Admixture:   ___
Water:       controlled by moisture condition

โš ๏ธ Recipe quantities are intentionally blank. Fill only with the 6-inch ratio approved by management. The 6-inch ratio may differ from the 8-inch ratio (MIB8_MIXING_V1) โ€” do not assume they are the same.

Correct Mix Signs โœ… / Wrong Mix Signs โŒ

โœ… CorrectโŒ Wrong
Mix holds shapeToo wet
Not too dryToo dry
Not sticky/wateryCement lumps
Uniform colourUneven colour
No lumpsSoil stones/waste visible

[PHOTO: Correct mix] [PHOTO: Wrong mix]

6. Do / Don't

โœ… DoโŒ Don't
Add water graduallyPour all water at once
Dry-mix before adding waterFeed machine with lumpy mix
Use the approved 6-inch ratioReuse the 8-inch ratio by habit

7. Checklist

[ ] Product confirmed as MIB 6-inch
[ ] Materials checked
[ ] Approved 6-inch ratio used
[ ] Water added gradually
[ ] Mix uniform, no lumps
[ ] First 20 bricks produced for approval

8. Records To Update

9. Escalation Rule

Inform Ram/Srinivasan if the approved mix cannot achieve correct consistency or if material quality is causing repeated bad mixes.

10. Common Mistakes

11. Improvement Suggestion

If you find a better way to do this process, add a comment below or submit an improvement request in the SOP Improvement Register.


Automation Readiness

Telegram command: /mix6
n8n workflow:     wf_mib6_mixing_v1
Odoo object:      mrp.bom / mrp.production
Approval role:    Factory Supervisor
Supabase table:   mix_batches
Status:           Future automation